Risk assessment and method statement
- Sections in the RAMS pack
- 9
- Computed on this page from the inputs below
- Person-days on the task
- 20
- Computed on this page from the inputs below
- Person-hours on the task
- 160
- Computed on this page from the inputs below
- Briefing time, hours
- $2.33
- Computed on this page from the inputs below
Every figure on this page is computed from the inputs you enter, by the method stated below it. The only constants DailyLogDesk supplies are the published reporting clocks and assessment steps, each cited where it is used. The defaults are a worked example to replace with your own.
Email me this result
We will send you these figures and a link back to them. One email, nothing else unless you tick the box.
The figures above start from a worked example (9). Change any input and the answer updates as you type.
Download the Risk assessment and method statement worked example (CSV)
This sizes a risk assessment and method statement for a construction task before anyone writes it. Enter the steps in the method, the operatives, the duration, the hours per day, the permits to work involved, the PPE items, the briefing time per operative and your loaded rate, and the page returns the sections the RAMS pack needs, the person-days and person-hours on the task, the briefing time including the permit issue, and what the briefing and the labor cost. A RAMS pack is a document with numbers in it; these are the numbers.
The method statement is the sequence, the risk assessment is the why
The two halves of a RAMS pack answer different questions: the risk assessment says what could hurt someone and what controls stop it, the method statement says in what order the work is done so that those controls are actually in place when they are needed. The page counts the sections for both, adds one for each permit to work, and the risk assessment tool on this site scores the assessment half.
Permits add sections, and they add time
Hot work, work at height and confined-space entry each bring a permit, a named issuer and a briefing before the task starts. The page adds the permit's sections to the pack and its hours to the briefing, so the RAMS you send the main contractor is the RAMS you can actually deliver on the morning.
Brief every operative, and price the briefing
A RAMS nobody on the task has read is a document, not a control. Twenty minutes per operative with a signature at the end is the norm, and the page prices it at your loaded rate so it is in the quote rather than eaten. The person-hours on the task sit beside it so the briefing reads as the small fraction it is.
Where the constants in this tool come from
HSE, Risk assessment: steps needed to manage risk. The assessment half of the pack follows the HSE's five steps; the method statement is the sequence that applies the controls.
Risk assessment and method statement: common questions
Is this a free risk assessment and method statement template?
Yes: the pack size, the person-hours and the briefing cost are computed here for free with no account, and you can print the figures. DailyLogDesk Pro builds the RAMS document from them with your company name on it, files it against the project with the risk assessment, and collects the briefing signatures.
Who has to sign a RAMS?
The person who wrote it, the supervisor responsible for the task, and every operative who was briefed on it. The page counts the operatives so the signature sheet has the right number of lines; Pro collects them.
How long should a method statement be?
As long as the sequence of work, and no longer. Eight sections cover a straightforward task; each permit adds its own. A RAMS pack that runs to forty pages for a two-day job is one nobody on site will read.